Full Diagnosis
Indicates that the initial check (test run) operation required after installation or a control reset has not been completed, so the chiller control holds startup in a safe, non-running state — this is a commissioning-status flag rather than an active hardware fault. It differs from U4, U6, and U8, which all report an ongoing communication breakdown on a specific wiring segment (outdoor-to-indoor, indoor-to-indoor, or between remote controllers) rather than an incomplete commissioning step. Running the manufacturer's check/test operation from the controller typically clears this code once wiring and addressing are confirmed correct.
All Recorded Causes
Check/test run procedure never performed after installation or after a controller replacement. Check operation aborted partway through. DIP switch or field setting left in test mode. Address or wiring verification left incomplete. Control PCB replaced without re-running startup commissioning.
Verify Before Replacing Parts
- Confirm the exact Daikin model family and chiller context before acting on a generic code description.
- Confirm board LEDs, wiring polarity, and model compatibility before replacing control boards — this Daikin fault points at check/test run procedure never performed after installation or after a controller replacem….
- Check for intermittent communication faults caused by connectors, moisture, or damaged harnesses, and rule out check operation aborted partway through.
- After the correction, run the system long enough to confirm the chiller fault does not return under normal load.